KST Infrastructure Limited

Construction Updates

On 19th Sep 2017

TOWER B


Structure work till basement + 15th floor complete
Railing & chaukhat work complete
Complete internal & external plastering work
All boundary wall foundation structure has been complete
Kitchen & toilets work till 5th floor in progress
Corridor marble work till 7th floor in progress
External basement work in progress

TOWER F



Structure Complete
TOWER D



Structure Complete
TOWER G



Structure Complete
TOWER C



14th Slab About to complete
TOWER A



Basement + 2 level complete
and 3rd level in progress